Mr. Nguyen Thai Son - Chief of Office of the National Steering Committee for Electricity Development has just had a working program to inspect and urge the implementation of power transmission projects serving Laos' electricity import in Nghe An.
Electricity PMU 1 discussed the plan of the line and connection point on the border between the two countries with Phongsubthavy Group - the investor of the Nam Mo - Tuong Duong 220kV transmission line project (section in the territory of Laos). On April 1, 2020, the two sides signed a memorandum of understanding at the border connection point. On May 17, 2020, Phongsubthavy Group issued a written notice on the progress of project implementation in accordance with the previously agreed schedule.
Regarding the Environmental Impact Assessment (EIA) report, PPMU has sent documents to the People's Committees of Tuong Duong district, Ky Son district and other organizations and communities for EIA consultation. Currently, community consultation has been completed in the localities where the line goes through. The Board will report to EVN through the EIA before submitting it to the Department of Natural Resources and Environment of Nghe An province for consideration and approval.
Electricity PMU 1 discussed the plan of the line and connection point on the border between the two countries with Phongsubthavy Group - the investor of the Nam Mo - Tuong Duong 220kV transmission line project (section in the territory of Laos). On April 1, 2020, the two sides signed a memorandum of understanding at the border connection point. On May 17, 2020, Phongsubthavy Group issued a written notice on the progress of project implementation in accordance with the previously agreed schedule.
Regarding the Environmental Impact Assessment (EIA) report, PPMU has sent documents to the People's Committees of Tuong Duong district, Ky Son district and other organizations and communities for EIA consultation. Currently, community consultation has been completed in the localities where the line goes through. The Board will report to EVN through the EIA before submitting it to the Department of Natural Resources and Environment of Nghe An province for consideration and approval.
Mr. Bui Phuong Nam added that the goal of the Board, in September 2020, will be submitted to the Ministry of Industry and Trade for appraisal of the basic design, it is expected that the Feasibility Study Report will be approved in December 2020. Construction commencement is in 11/2021 and is accepted, handed over and put into use in the second quarter of 2022.
“Currently, the project is facing a number of difficulties and obstacles in the process of implementing investment preparation procedures and policy on conversion of forest use purposes. Therefore, it is suggested that the People's Committee of Nghe An province, the Department of Natural Resources and Environment, the Department of Agriculture and Rural Development, the People's Committees of Ky Son and Tuong Duong districts soon add the project to the land use planning and plan of the locality. Phuong "- said Mr. Nam.
In addition, PPMU also requested the province and relevant departments to guide in the work to change the policy of forest land use purposes, compensation and site clearance.
Speaking at the meeting with the Departments, branches and localities of Nghe An province, Mr. Nguyen Thai Son - Chief of Office of the National Steering Committee for Electricity Development said: Forecast of electricity supply in the period of 2021 - 2025 will be more difficult. Importing electricity from Laos is one of the suitable solutions to meet the electricity demand in the immediate and medium term, especially for Nghe An. Over the past time, EVN and related units have made great efforts to speed up the preparation of investment in the construction of transmission grids to import electricity from Laos. Although certain results have been achieved, however, through the survey and actual recognition of the mission, there are still many difficulties that need to be solved.
Mr. Son suggested the Provincial People's Committee, Departments, Branches and related agencies of Nghe An province continue to pay attention, focus on supporting the investor to complete the procedures of projects, including: Complementary work. 220kV project serving the import of electricity into local land use planning and plans, proposing the Government to apply for a policy of changing forest use purposes, ..., in order to urgently complete investment preparation procedures. , speed up the implementation of investment projects.
"Departments and agencies need to consider this as a local responsibility and responsibility, with specific and clear instructions, creating conditions for EVN and consulting units to complete their tasks. Projects and consultants need to study and adjust a number of technical solutions to suit the planning, facilitate the overall connection to the power grid in the future, as well as adjust some structural solutions to minimize environmental impacts. to reduce the impact on natural forests ", Mr. Son emphasized.
Mr. Son also asked EVN to strengthen working with power investors in Laos to urgently achieve the target of purchasing electricity from this country to reach 3,000MW by 2025 and 5,000MW by 2030 with the electricity price bracket approved by the Prime Minister. Government approval. Continue to coordinate with Lao investors to research suitable connection plans for power source projects, coordinate with Lao partners in research and development projects including thermal power, hydroelectricity, renewable energy imported to Vietnam. Urgently complete the plan to connect the overall power system of the two countries Vietnam - Laos until 2030.
In addition to the 220kV Nam Mo - Tuong Duong transmission line, in order to serve the import of electricity from Laos, it is also necessary to build transformer stations (TBA) and the connection line system such as: Tuong Duong 220kV substation and connection lines, TBA 220kV Nam Cam and connection lines, 220kV Tuong Duong - Do Luong substation, 220kV Do Luong - Nam Cam transmission line.
According to EVN